How many days in advance should you call the notification center before digging?

Prepare for the APM Apprentice Test. Engage with interactive quizzes, flashcards, and multiple choice questions. Study effectively and ace your APM exam!

The correct answer is that you should call the notification center at least 2 days but not more than 5 days in advance before digging. This timeframe allows sufficient notice for the notification center to process the request and inform affected utility companies to mark their underground lines. By notifying within this window, you ensure that all safety protocols are adhered to, minimizing the risk of damaging existing infrastructure and ensuring the safety of the digging project.

This approach reflects standard practices aimed at promoting safety and efficiency in construction and excavation activities, further underscoring the importance of advance communication with utility providers. The specified range of days balances the needs of both the notification center and the digger, helping prevent delays while also allowing for adequate safety measures to be put in place.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy